10
Mar

Four new Quay Cranes for RWG

After a sea voyage of approximately two months, the Zhen Hua 8 arrived at Rotterdam World Gateway (RWG) on Monday March 10th 2014 around 13.00 PM. Due to favourable weather conditions, the ship arrived earlier than expected. The Zhen Hua 8 delivered three Deep Sea Quay Cranes and one Barge/Feeder Quay Crane. In the coming days, the cranes will be discharged from the ship onto the quay. With the arrival of this ship, all three Barge/Feeder Quay Cranes of RWG are present on the terminal. After discharge, seven out of in total eleven Deep Sea Quay Cranes will have been delivered. The terminal is beginning to take on its definite form.